I hired a construction company in Malta to carry out renovation work on my property, and the agreed completion date has now passed by several weeks with the work still significantly incomplete, and I’ve received only vague explanations for the delay. What are my options here?

Site Administration 15.08.2026
reply date: 15.08.2026

Your specific rights and options depend significantly on what your construction contract actually says about timelines, delays, and remedies, since a properly drafted construction contract would typically address matters such as the agreed completion date, any provisions for extensions of time in specific circumstances, and consequences for unjustified delay, such as liquidated damages clauses, meaning reviewing your actual contract terms is the essential starting point before assessing what remedies genuinely apply to your situation. Even without specific delay provisions in your contract, under general principles of Maltese contract law found in the Civil Code, Chapter 16 of the Laws of Malta, a significant, unjustified delay in completing contracted work can constitute a breach of contract, potentially entitling you to damages reflecting your actual demonstrable losses caused by the delay, such as additional accommodation costs if you've been unable to occupy the property, though properly establishing and quantifying this kind of claim generally requires clear supporting evidence. Before escalating to formal legal action, it's worth sending the contractor a clear written notice referencing your contract terms, formally requesting a specific revised completion date, and documenting the vague explanations you've received to date, but given the potentially significant financial impact of a stalled renovation, consulting a lawyer to review your specific contract and advise on your strongest options would be a sensible next step if informal communication doesn't resolve the delay.

Похожие вопросы

Can I refuse to complete a purchase if the survey reveals problems?

1 answer
23.07.2026
I signed a konvenju to purchase a property in Malta, conditional on a satisfactory survey, and the survey I've since had carried out has revealed some genuine structural concerns I wasn't expecting. I want to understand whether I can actually withdraw from the purchase based on this survey result without facing the usual penalties for failing to complete.
Читать далее
0
0
1

Can my Malta condo association restrict what I do with my own unit?

1 answer
28.06.2026
I own an apartment within a larger residential development in Malta that has some form of condominium or owners' association governing shared areas. I want to understand the extent to which this association can actually restrict what I do within my own individually owned unit.
0
0
2

Can I be evicted from a rented property in Malta without proper notice?

1 answer
02.08.2026
I've been renting a property in Malta and my landlord has just told me verbally that I need to move out within a week, without any prior formal written notice or clear explanation. Is this actually legal, or am I entitled to more formal notice before being required to leave?
0
0
2

Can I be forced to sell my share of jointly owned property?

1 answer
24.08.2026
I co-own a property in Malta together with another family member, but we disagree about what should happen with it, they want to sell, and I want to keep it. Can they actually force a sale of the whole property, or force me to sell my share, against my wishes?
0
0
5
Show all